Seven years to build and three times the original cost – The Bale House WILL open this summer

The Bale House, the controversial new Country Park visitor centre that has cost more than £1.1m and taken seven years to come to fruition will open, at last, later this summer.

Opening this summer.

Described in January by Councillor Andy Batsford as a, “…great public asset for the town,” the building will be up for discussion tomorrow tonight (June 16th) when members of Hastings Borough Council’s (HBC) Labour-only cabinet rubber stamp the finer detail of the contract that will govern how the building is run in the coming years.

A report to cabinet will tell councillors that The Bale House is, “…due to open this Summer, 2021.”

They will hear that council officers have negotiated a ten-year agreement with Groundwork Trust to manage the centre on the council’s behalf: “Authorisation to proceed with a lease and management agreement are required to enable an operator to be appointed, so the new visitor centre can open this Summer,” councillors will be told.

But only part of the draft lease and the draft management agreement will be discussed in public with councillors believing the financial aspects of the deal are ‘commercially sensitive’ and it is recommended they should be discussed in private session.

The Bale House was constructed in partnership with Groundwork South and attracted funds from the European Union under the Interreg scheme that encouraged the use of straw bales for construction. The ten-year lease councillors are being asked to approve includes a commitment to the centre becoming cost neutral to the council after three years.

The building which was touted as a state of the art, environmentally sound project has been beset by delays and escalating costs. The straw bales used for the building were bought in 2015 and lay in storage for three years before they were used and at the start of this year HBC had to commit to pumping a further £340,000 in to the project to see it finished. It wasn’t the first time the council had had to pledge extra cash and the January cash injection brought the cost of the finished building to three times the original estimates.

Cabinet members will be told: “Groundwork accessed significant European funding to match the council’s funds to build the new centre. They were awarded additional grants from Heritage Lottery to invest at Hastings Country Park and have been awarded significant funding through the CHART programme to work with communities around town.

The interior awaiting fitting out.

“They are proving to be one of the most significant and successful third sector partners for the council and remain committed to working with the council for the benefit of our local communities.”

Mike Hepworth, HBC’s Assistant Director Environment and Place told councillors in January: “The people of Hastings will have a brilliant new environmentally sustainable community facility,” and he predicted that it will become a major attraction for people from Kent, Sussex and beyond.

But observers have also questioned the assertion that the centre will, in itself, attract people. In March 2015 when the planning committee approved the original plan the report to planning committee members said it was not expected the visitor centre would be a destination in its own right, it said: “Although the visitor centre may attract more footfall than the existing centre, it is not envisaged to be a destination in itself which would attract a significant increase in traffic.”

3 thoughts on “Seven years to build and three times the original cost – The Bale House WILL open this summer

  1. You really could not make this up! A plain looking building like this has taken seven years to build and had over a million quid thrown at it. All it displays to the local electorate is a council and councillors who are not fit for purpose. And how often do you hear these councillors bleating on about how poor financially they are.
    As for Cllr Batsford’s comment about it being a “great public asset for the town.” Followed by Mike Hpeworth’s belief it will be it will ” become a major attraction for people Kent, Sussex and beyond.” Really ?
    What world do these two live in. This is hardly anything to be proud of.
    As I have said before this is the “Folly” of Hastings.
    Even now it is completed they are still working out the lease issues. Why didn’t they do that years ago.

  2. I was interested in the word destination as used in this article. It is a phrase oft used by HBC. I’m sure they don’t really understand its meaning being a place that people will make a special trip to visit.

    They have used this term to describe their daft and grossly unpopular proposal to concreate over the old bathing pool site on Seaside Road. If you haven’t heard, HBC proposes to create a ‘Destination location’ (their description not mine) by cramming 152 residential units into an area that has no infrastructure to support it. Who in their right minds would want to visit a housing estate, or a house made of grass for that matter?

  3. I think many people when they look at this meagre and sadly uninspiring building will conclude that £1.1m was a lot of money to be spent. Especially when considering this didn’t include the cost of the land it is sitting on which in any new build house would be in the region of 30% of the price. Still, it is there now and we must hope it it is well received and well used by young and old alike because the taxpayers of Hastings could be paying for it for many years to come.

Leave a Reply

Your email address will not be published. Required fields are marked *

Related

Was 2018 the start of the Green trend in Hastings?

When the Green’s then co-leader Caroline Lucas visited Hastings for a bit of pre-election campaigning in 2018 she said that securing a Green councillor on Hastings Borough Council (HBC) would be a, “tremendous breakthrough” and “the start of a trend”. Last week, just six years later, the Greens became the biggest group on HBC. Listen […]